Frequently Unanswered Questions:  What’s Missing from the Response to Town Councilors’ Questions About the Jones Library?

0
questions,  answers

Photo: istock

By Jeff Lee and Maria Kopicki

The following document was placed in the packet for the Town Council meeting of March 24,  2025. The document was not on letterhead and did not note its author or source.  We have added to the document our annotations, pointing out questions that have not been fully answered, misleading answers, and questions that still need to be asked (and answered).  We continue to call for a full and transparent accounting of the real costs of the Jones Library expansion (see e..g. here and here), which is not provided in this document. 

The project represents a considerable and growing financial liability to the town and in this unstable fiscal and political and environment, the risks to the town become more profound with each passing day.  The town has an obligation to clearly document what the project will cost and how the town will pay for it and the project should not proceed until such documentation is provided.

Town Council Questions 
March 24, 2025 

This document answers the questions posed by members of the Town Council with the best information we have available. 

1. Costs and Status of Construction

a. Current updated costs: 

i. The latest project cost estimate was developed on November 7, 2024  following receipt of updated contractor bids. The total project cost remains $46,139,800, which includes $3,562,800 (10%) in available  project contingencies. 

b. Slate roof: 

i. The Library architect, Finegold Alexander Architects (FAA),  estimated the additional cost of shifting from synthetic to natural slate  roofing to be $228,000. This cost will be paid out of project contingencies. 

c. Preservation and restoration of woodwork: 

I. Notably, approximately 80% of the existing mahogany woodwork will remain in place. Of the woodwork to be removed, repurposing of several portions was included in the rebid scope of work and so work  is already priced into the project. 

ii. The draft Memorandum of Understanding (MOA) with the  Massachusetts Historical Commission (MHC) commits to three additional locations of woodwork removal and potential repurposing  including the doorway lintel and trim at the east secondary stair, the  arched doorway and fanlight window in the director’s office, the   paneling around the door in the east wall of the west secondary stair,  and the two arched panels in the east wall of the young adult reading  room. No detailed estimate of the cost of this additional work has been developed, but it will likely be in the range of $25,000 to $75,000. Any remaining unused mahogany woodwork will be offered to an  architectural salvage company for reuse elsewhere at their expense in accordance with the Jones Library deaccession policy. Any additional  costs will be paid out of project contingencies. 

d. Holding bids, including subcontractors: 

i. Discussions are ongoing with sub-bidders and the low general bidder. Some have agreed to extend their bid pricing through the end of  April, a few have not, and several have not responded. In the event  that a low sub-bidder is not willing to hold their bid pricing,   Massachusetts General Law allows for a municipality to move on to  the next lowest bidder and adjust the general contractor’s contract  value accordingly. 

e. Owner’s Project Manager (OPM): 

i. Colliers was the OPM for the project. On May 21, 2024, the Town  asked Colliers to halt all activity as we worked through the process. This has saved about $200,000 in project costs. The work has been  done by the Town’s Capital Projects Coordinator, Bob Peirent. Colliers will be re-engaged as OPM when the project moves into  construction. The Town has maintained contact with Colliers, and  they have confirmed their availability to perform this work. 

f. Timing for new and revised work: 

i. Rebidding the roof work will occur after a contract has been executed  with a general contractor. This will likely be in late spring/early  summer 2025. 

g. Can all this be done including contracting by the end of April? What happens if  costs are higher than the budget? 

i. That is the plan. The latest project budget summary updated to reflect  the bids that were received in November 2024 indicated an available project contingency in excess of $3.5 million. Any costs in excess of  what are shown on this summary will reduce this available  contingency amount. 

2. Federal Grants

a. Do we have assurances that the HUD and NEH grants are secure? 

  1. We recently received an executed grant agreement with HUD. The executed NEH grant agreement is pending. 
  2. HUD grant: What is an update on HUD and Section 106 Review? 

An environmental review in accordance with HUD  specification has been drafted. This review cannot be finalized and released for public comment until the  Section 106 Historical Preservation process is complete.  It is expected to be released within a few days of  receiving a signed Memorandum of Agreement f rom  the Massachusetts Historical Commission. 

2. HUD grant payment: What is the timing of grant payments? 

1. The $1,110,661 in HUD grant funds have been  approved for reimbursement of project soft costs. As   noted in HUD’s FY2023 GRANT GUIDE, payment of  soft costs can be made once a Grant Agreement is   executed by HUD. We anticipate submitting a reimbursement application to HUD within the next few   weeks. Follow-up discussions with HUD staff  environmental review have indicated that full release of   grant funds will not occur until the project-specific environmental review is completed. The amount of our   initial reimbursement request will be confirmed after  further discussions with HUD staff. The balance of the  funds will be requested for reimbursement after the  environmental review process has been completed. 

iii. NEH grant: 

1. What is an update on the grant payment? 
1. A signed agreement with NEH for their $1,000,000  grant will be issued once the Section 106 Historical   Preservation process has been completed and the   required 4:1 nonfederal funds match is certified. 

2.NEH remains committed to providing funding for this project and as recently as February 24, 2025, stated in  writing that they will be providing federal financial  assistance to the Jones Library, 43 Amity Street,   Amherst, Massachusetts 01002, through an Infrastructure and Capacity Building Grant (CHA  292057). 

3.Full funding will not be released until it can be certified that the required matching funds have been expended   on the portion of the project funded by the grant, the Jones Library Humanities Center. That will likely be at least 6 months from the start of construction. 

2. What is the plan if the review is not completed by April 30th? Could a contract be signed in the hopes that the Section 106   Review will achieve a satisfactory resolution? 

1. Reviewing options for this contingency. 

3. Massachusetts Board of Library Commissioners (MBLC)

a. MLBC originally planned 4-5 distributions of the $13,871,314 grant. When will Amherst receive the added funds for inflation – $1,694,158 Pandemic Escalation?

i. The Town has received a payment from the MBLC in the amount of $2,774,263 

ii. Once the contract with a General Contractor is signed, the MBLC will  send Amherst two disbursement payments in FY25 ($5,548,526 total);  three disbursement payments (including the extra for Pandemic relief) will remain. Disbursement payments are sent after certain  milestones are met. Normally, only one disbursement payment can be  sent in any given fiscal year; this year is different because our project  is so far behind (i.e., the MBLC has begun a new grant round, and it is important that they complete our grant round so they can begin to  disburse payments to new awardees). 

4/Jones Library Endowment

a. What was the endowment as of end of February? 

i. As of 2-28-25 the foundation account’s value was $9,006,334.95. 

b. What is the expected annual draw in percent or dollars? 

i. The 4% draw for FY25 was $354,619. 

ii. The 4% draw for FY26 is projected to be $350,858. 

c.Has this already been adjusted for the payment for additional architect work? 

i. The FY25 draw of $354,619 does not include summer 2024 payments to Finegold Alexander Architects. 

d. Has Woodbury been distributed to Friends for Project? What is the balance of this  fund? 

i. Funds will not be withdrawn until we have a project certain.  ii. As of 2-28-25 the Woodbury Fund’s value was $792,916.71.

5/ Fund Raising

  • What is the current status of Fund raising? 
Photo: amherstma.gov

b. Is there any concern that economic uncertainty will impact fundraising, especially donations from individuals? 

i. Unknown 

c. Has Amherst College distributed a second payment? 

i. No. 

6. Finances

a. What assurance can the Trustees provide the Town for payment of the $7 million  dollar gap in their share. 

i. The Trustees have signed an MOA with the Town that provides  assurances that the Trustees will meet its share. 

b.Is there an arrangement with a Bank or Other loan entity to provide full payment  as agreed to in the MOA? Would this be a mortgage? Or loan against the  endowment? 

i. Many conversations have been held with MassDevelopment and local banks regarding borrowing funds if the need arises. The Trustees will  make the best decision when the time comes to ensure the Endowment  and Library services continue in perpetuity. 

c. Updated cash flow and principal interest projections 

i. Will be updated when the project is ready to move forward.

d. Does the town council have the authority to approve an additional $7m in  taxpayer money to pay for the library budget shortfall without a town vote? 

i. Yes, this is true for any Town project. The Town Council is the Town  body with the authority to borrow funds upon request by the Town  Manager. If the funds are to be borrowed, a 2/3 vote of the Town   Council is required. No Town-wide vote is required unless the   borrowing is contingent on a debt exclusion override. 

e. Who is responsible if there is a shortfall? 

  1. The Massachusetts Board of Library Commissioners has committed  grants of $13.8m + $1.7m = $15.5m 
  2. The Town Council has committed to borrow = $15.8m 
  3. The Town of Amherst Community Preservation Act Committee and Town Council have approved a grant = $1m  iv.
  4. The Library Trustees have committed to raising the remainder  through Federal and state grants and private fundraising.  Total approved project cost – $46.1m 
  5. The Trustees have agreed to use either the Library’s endowment or  other soruces of funds available to it, which may include a bank loan,  to pay its share.

Spread the love

Leave a Reply

The Amherst Indy welcomes your comment on this article. Comments must be signed with your real, full name & contact information; and must be factual and civil. See the Indy comment policy for more information.

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.